Nepal inaugurates its first modern road tunnel after seven years of work
Published: 11:37 am Jul 27, 2026
Key Takeaways:
- 2.68-km Nagdhunga–Sisnekhola Tunnel inaugurated; initially open only to emergency vehicles
- Project includes main tunnel and 2.56-km rescue tunnel with advanced safety systems
- Built by Japan's Hazama Ando Corporation, financed by Nepal and Japan at Rs 29 billion
- Once fully operational, tolls will apply; cars to pay Rs 65 entering Kathmandu, Rs 60 leaving
Connecting Dahachok in Chandragiri Municipality, Kathmandu, with Sisnekhola in Dhunibesi Municipality, Dhading, the tunnel is expected to cut travel time on the congested Nagdhunga section by nearly an hour. The project comprises a 2.68-km main tunnel and a 2.56-km emergency rescue tunnel equipped with CCTV cameras, fire-fighting systems, emergency communication facilities, ventilation and other safety features.
Pedestrians, motorcycles, three-wheelers and vehicles carrying fuel, gas, explosives or other flammable materials will not be allowed to use the tunnel. Once fully operational, toll charges will apply, with cars and vans paying Rs 65 when entering Kathmandu and Rs 60 when leaving. Higher rates have been fixed for minibuses, buses, trucks and heavy vehicles. Construction began after the foundation stone was laid by then Prime Minister KP Sharma Oli on November 21, 2019. Although scheduled for completion within 42 months, the project was delayed by the COVID-19 pandemic, compensation disputes and other challenges.
Built by Japan's Hazama Ando Corporation, the project was financed through concessional loans from the Japanese government and investment by the Government of Nepal. The total project cost rose to around Rs 29 billion after additional funding was provided during construction.