Ten machines, 30 personnel deployed to reopen Krishnabhir road as festive season deadline approaches
Published: 12:05 pm Sep 12, 2026
Key Takeaways:
- Highway blocked since Aug 30 after Trishuli River erosion caused subsidence at Krishna Bhir
- 10 machines, 30 personnel working 12–14 hours daily, with floodlights enabling night construction
- New 250m track being cut through hillside, based on recommendations from geotechnical assessment teams
- Crisis revives memories of 1998–2001 landslides, when the highway was blocked for 11 days and required Rs35m control works