Bhedetar–Rabi–Ranke road: 8 years on, only 71% complete as deadline nears
Published: 01:00 pm Sep 20, 2026
Key Takeaways:
- Only 71% of physical work has been completed on the nearly 100-km Bhedetar–Rabi–Ranke road after eight years
- The latest six-month deadline expires on Nov. 3, but officials say remaining works are unlikely to be completed on time
- Delays have been linked to Covid-19, land disputes, forest clearance issues, utility relocation, landslides and difficult terrain
- Residents and local leaders say the long-delayed project is affecting travel, tourism and local livelihoods