Why the delay?
Why the delay?
Published: 08:30 am Jul 23, 2016
KATHMANDU: The developer of Upper Trishuli-1 hydroelectric project was initially planning to begin project construction in 2014. But that deadline could not be met due to delay in signing of the PDA. One of the reasons for delay in PDA signing — apart from frequent changes in the government — was the government’s inability to decide on whether to sign dollar-denominated PPA with the project developer as requested. READ ALSO: