Contract termination delays construction of Tanahu hydro

THL plans to start work from January

Himalayan News Service
Share Now:

Kathmandu, August 27

Following the contract termination with the Italian contractor Co-operativa Muratori e Cementisti (CMC) di Ravenna, the construction of the 140-megawatt Tanahu hydropower project, which is a capacity reservoir project being developed by Tanahu Hydropower Ltd (THL), will now begin in January.

Earlier, there were plans to start the construction of the project from the beginning of 2019. This change in schedule means that the starting time has been extended by one year.

THL had officially terminated the contract with CMC on March 6. Earlier, THL — a fully-owned subsidiary of Nepal Electricity Authority — had hired CMC to divert the flow of the river, build a dam and complete head works. CMC was selected as the preferred bidder as it had made the lowest bid of Rs 20.64 billion.

Pradip Kumar Thike, managing director of THL, informed that the construction has been delayed as the project had to terminate the initial agreement with CMC and issue another tender for the related works. “We have to follow the Public Procurement Act, which means that we have to abide by all the provisions of the act,” he stated. “Hence, we have set a target to start construction of the project from January next year.”

According to him, 19 companies had shown interest to build the aforementioned works. Among them, only four companies — China Gezhouba Group Company, Sinohydro Corporation Ltd, China National Electric Engineering Co and Song Da Corporation Vietnam/Kalika Construction JV — have submitted the technical and financial proposals for the project.

“We are now assessing the technical proposals of the four companies. After we finalise the detailed study of their technical proposals, we will forward them to the Asian Development Bank for its approval and only after that will we open the financial proposals,” he mentioned.

The second phase of construction, including tunnel construction, procurement of hydromechanical equipment, electromechanical equipment installation and other tasks, will be carried out by Sinohydro Corporation Ltd.

As per Thike, Sinohydro has already constructed the necessary infrastructure — office building, workers’ housing and roads. The Chinese firm has already finished its survey of the site and is about to finalise the design.

Likewise, the project has already assigned the responsibility to construct the 220 kVA double-circuit line from Damauli to Chitwan, which is the third phase of construction, to an Indian company called KEC International. The company is currently doing survey works of the transmission line.

The total cost of the project is estimated at $506 million, of which the Asian Development Bank will provide $150 million, Japan International Cooperation Agency will contribute $184 million, European Investment Bank will give $85 million and NEA will chip in $87 million. It is expected to be completed in the next five years.

The project has made 16.17 per cent physical and 12.33 per cent financial progress so far.


A version of this article appears in print on August 28, 2019 of The Himalayan Times.


Follow The Himalayan Times on Twitter and Facebook

Recommended Stories:

More from The Himalayan Times:

Diogo Jota

Liverpool maintain 100% start with win over Arsenal

LIVERPOOL: Premier League champions Liverpool maintained their 100% start to the season with a 3-1 win against Arsenal at Anfield on Monday leaving them level on nine points with pacesetters Everton and Leicester City. The visitors took the lead through an Alexandre Lacazette strike but L Read More...

Fulham, Aston Villa, Ivan Cavaleiro, Matty Cash

Villa beat Fulham 3-0 to move into top four

LONDON: Aston Villa moved into the Premier League top four after they strolled to a 3-0 win at Fulham thanks to goals from Jack Grealish, Conor Hourihane and Tyrone Mings in a lopsided contest on Monday. The result left Villa, who narrowly avoided relegation last season, fourth on a maximu Read More...

Private hospitals, labs to charge Rs 3,899 for PCR test

KATHMANDU, SEPTEMBER 28 Private hospitals have fixed their own rate for conducting polymerase chain reaction tests, saying that the fee allocated by the Ministry of Health and Population was too less. Eight private hospitals and labs, including HAMS Hospital, Star Hospital, B&B Hospital an Read More...

President issues ordinances on acid attack punishment, acid sale regulation

KATHMANDU, SEPTEMBER 28 President Bidhya Devi Bhandari today issued two ordinances to increase jail sentence for acid attackers and to regulate the sale and distribution of acid and other harmful chemicals. One of the ordinances amended the new penal code, proposing to increase jail term for a Read More...

Editorial: Unemployment problem cannot be addressed unless all levels of govt work together to create jobs within the country

The unemployment problem cannot be addressed unless all levels of govt work together to create jobs within the country Unemployment is a big problem in Nepal. That is why youths in large numbers migrate to other countries, mostly India, the Middle East, Malaysia, South Korea and Japan, where they e Read More...

Ayurvedic literature: Delving into its history

The travelogue of Chinese pilgrim Faxian was the earliest testimony to describe the healthcare system in ancient South Asia. It is close to the description by the earliest Ayurvedic compendium, Charaka Samhita Ayurveda has become a buzzword in the contemporary setting of medicine in the era of COVI Read More...

Six student leaders arrested for staging protest outside Chinese Embassy in Kathmandu

KATHMANDU, SEPTEMBER 28 Six student leaders of Nepal Student Union, the student wing of major opposition Nepali Congress, were arrested today for staging a protest outside the Chinese Embassy at Baluwatar against the alleged border encroachment by the Chinese side in Humla district. The NSU le Read More...

Woman found dead in Saptari district

A police team has been deployed from Province Police Office, Janakpur, to investigate the case RAJBIRAJ, SEPTEMBER 28 A 50-year-old woman was found dead at Mayanakaderi village, Ward No 2 of Tirhut Rural Municipality, Saptari, yesterday. The body of Dayaman Devi, wife of local Shiv Narayan, w Read More...