Kulekhani III likely to commission power before Vijaya Dashami

Himalayan News Service
Share Now:

Kathmandu, October 1

As per the revised plan, the 14-megawatt Kulekhani III cascade hydropower project is likely to be connected to the national grid before Vijaya Dashami. The project has already started test generation from first week of September.

“We plan to connect the project to the national grid within a week,” informed Kamal Acharya, project head of the Kulekhani III project.

As per him, the project has already completed all the necessary physical infrastructure works, including construction of substation and transmission line, and also installed wires that connect to the power house and the substation.

Acharya further said that the generated electricity will be connected to the Hetauda-Kulekhani transmission line. For the final test, a Chinese technical team will arrive tomorrow and will formally inaugurate the project.

The Kulekhani III hydropower project is located in Indrasarobar Rural Municipality in Makawanpur district.

As per the initial plan, the project was scheduled to start commissioning power from 2012, but the project was delayed due to continuous problems related to the contractor. Another problem that delayed the completion of the project was the frequent change in policy along with the change in the government.

The Kulekhani III project was mainly delayed due to dilly-dallying by Chinese construction company, Jheijian Jialin, which was awarded the contract to complete the electromechanical and hydromechanical works. The government had in recent times been applying due pressure on the contractor to complete its work on time.

Initially, the construction cost of the project was expected to hover around Rs 2.43 billion but after perennial delays, it has now escalated to around Rs five billion. Also, the initial projection had estimated production cost per megawatt power to stand at Rs 173.6 million. However, as per revised estimate, it is now expected to cost above Rs 310 million per megawatt.

At present, Kulekhani I reservoir project has been producing 60 megawatts of energy and Kulekhani II, a cascade hydro project, has been producing 32 megawatts of power. After the Kulekhani III project starts commissioning power, the Kulekhani reservoir project’s capacity will increase to 106 megawatts.

 


A version of this article appears in print on October 02, 2019 of The Himalayan Times.


Follow The Himalayan Times on Twitter and Facebook

Recommended Stories:

More from The Himalayan Times:

Mitchell Starc, Australia

Bring on the pink ball for India series, says Australia's Starc

MELBOURNE: Australia paceman Mitchell Starc has never been a huge fan of the pink ball but would welcome the prospect of bowling it against India in a day-night test over the home summer. India declined Australia's offer to play a day-night test during their last tour in 2018/19 but board pre Read More...

Gharial crocodiles, Chitwan National Park

Ghariyal journeys 1,062 km to Hoogli

Chitwan, May 25 A gharial released in a river in Nepal has travelled over a thousand kilometres in the past two months. It was found in a river in India. According to Chitwan National Park Assistant Conservation Officer Bed Bahadur Khadka, a gharial with tagged number 687, which was released i Read More...

France coronavirus

France again ranks No. 4 in COVID-19 deaths as Spain revises tally

French coronavirus death toll at nearly 28,500 Increase in number of cases keeps slowing down France's death toll now well above Spain's PARIS: France again ranked fourth in coronavirus deaths after the United States, Britain and Italy, as Spain revised its tally down by nearly 2,000 Read More...

Inmates at risk of contracting coronavirus in Kathmandu valley

Kathmandu, May 25 About a month ago on April 22, two nurses working in the country’s largest prison at Sundhara tested positive for COVID -19 under the rapid diagnostic test. The test result sent a wave of panic among the 25,087 jailbirds, including 773 juveniles and additional 773 infants l Read More...

Strong winds wreak havoc in Rautahat

Rautahat, May 25 Strong winds destroyed properties worth millions of rupees in different parts of Rautahat district last night. Power supply was obstructed in the local level after the utility poles were broken. Two mango trees fell on houses due to the strong wind following rainfall at Read More...

Armyworm severely affects maize production

Kathmandu, May 25 The American armyworm has severely affected maize farming across the country this year as compared to previous year, hitting farmers who have already had to bear the brunt of the coronavirus pandemic. According to Centre for Crop Development and Agro Bio-Diversity Conservatio Read More...

Budget expectations

The government is all set to announce the budget for next fiscal year on Thursday and people involved in different sectors have various expectations. Amid this, The Himalayan Times spoke to a few tourism entrepreneurs who were not satisfied with the government’s policies and programmes to learn ab Read More...

Over 10,000 Nepalis enter country from Jamunaha border point in four days

NEPALGUNJ: Over 10,000 Nepalis have entered the country from Jamunaha border point in Banke district amid nationwide lockdown imposed by the government to curb the spread of COVID-19. A large number of migrant workers returning from India have been gathering at the border point with the easing of Read More...