Nepal | July 05, 2020

NEA terminates Dhalkebar contract

Says Chinese contractor intentionally delayed construction of substation

Himalayan News Service
Share Now:

Kathmandu, October 3

Nepal Electricity Authority (NEA) has terminated the contract of Dhalkebar substation as the Chinese contractor had intentionally delayed the works of the project, which is critical for Nepal-India electricity trade.

The Central China Power Grid International Economic and Trade Co Ltd, contractor of the substation, had delayed the works since long putting forward various demands, which are not related with the contract. The contractor had asked NEA to remove the component of Inaruwa and Hetauda substations from the project or provide actual additional cost that accrue while implementing the project.

“The contractor had hardly worked for seven months since the work started one-and-a-half years back,” said Radhesharan Mahato, project manager of Dhalkebar substation.

As per the contract between NEA and China Power Grid International Economic and Trade Co Ltd in June 2014, the substation was supposed to have been completed by September 2015. But the deadline was continuously pushed back as the Chinese contractor had sought additional incentives to complete the project on time.

NEA has already seized the bank guarantee of the contractor. However, the power utility has yet to select the next best option to expedite the project. After termination of the contract, NEA has a few options, like it can call for request for proposal (RfP) from the shortlisted companies, open a rebidding process or hand over a direct contract for remaining works to one of the earlier shortlisted companies.

According to Mahato, 85 per cent works of the project have been completed.

The Dhalkebar substation is a crucial project for cross-border electricity trade with India as the country plans to raise import of electricity via Muzaffarpur-Dhalkebar cross-border electricity transmission line. The country will be able to import an additional 100 megawatts of electricity on top of the existing 145 megawatts from India after the Dhalkebar substation has been charged at 220 kV, which is critical to end load-shedding, according to NEA officials.

Nepal-India energy secretary level talks held in February had also taken into account that the project will be completed by August this year. The Dhalkebar substation is being developed at a total cost of Rs 1.42 billion under loan assistance of the World Bank. Especially for projects funded by the World Bank, the executing agency has to release the payment for equipment to the contractor, after it submits the shipment order of the equipment.

“The contractors normally generate profit from the delivery of equipment despite low bidding for the field level works and they seem reluctant to complete the project works on time,” a high-level official at NEA told The Himalayan Times. “The NEA has also proposed to release 50 per cent of the payment for equipment only after the completion of works to make the contractor liable to complete the project works within the desired time.”

READ ALSO:


A version of this article appears in print on October 04, 2017 of The Himalayan Times.


Follow The Himalayan Times on Twitter and Facebook

Recommended Stories:

More from The Himalayan Times:

Locals at risk while crossing river using suspension bridge in Bajura

BAJURA: Incessant rainfall in Bajura has raised the water level of Budhiganga River to touch Taprisera suspension bridge leaving commuters, who use the bridge to cross the river, at a great risk. The bridge, which connects Tribeni Municipality and Budhiganga Municipality, is getting partially sub Read More...

Nepal logs two more COVID-19 related deaths on Saturday

KATHMANDU: Nepal has recorded two more COVID-19 related deaths, confirmed the Ministry of Health and Population, at its regular media briefing, on Saturday. A 44-year-old male, resident of Palungtar Municipality-7, Gorkha, has succumbed to the coronavirus infection. The swab sample of the decease Read More...

Bajhang Landslide Update: Four bodies recovered

BAJURA: Four persons, who were missing in the landslide that occurred at 2:00 am on Saturday in Mallesi of Kedarsyun Rural Municipality in Bajhang district, have been found dead. Bodies of 40-year-old Rammati Jethara and her 12-year-old son Prayag Jethara were found buried in the debris of the la Read More...

COVID-19 Update: 232 new cases, 272 recoveries, two deaths recorded today

KATHMANDU: Nepal’s Health Ministry, in its regular press briefing, shared the latest updates on coronavirus contagion from across the country, and government’s response to the health crisis. As of today, 246,297 tests through Polymerase Chain Reaction (PCR) method and 310,300 Rapid Diagn Read More...

THT logo

Woman dies after returning home from quarantine in Kailali

DHANGADHI: A woman has died after a week of returning home from a quarantine facility in Kailali, on Friday. A 48-year-old woman, resident of Godavari Municipality-10, breathed her last on Friday night while in home quarantine, according to mayor of the municipality, Hari Singh Saud. It has be Read More...

Netflix to continue streaming 365 Days amid calls for its withdrawl for glorifying sex trafficking

KATHMANDU: Netflix has decided to stand by Polish film 365 Days that has been accused of glorifying sexual trafficking, kidnapping rape. Netflix announced to continue streaming the movie on July 3 amid calls for its withdrawal including by British singer Duffy who said it glamorised "the brutal re Read More...

Disney+ unveil three movies for Comic-Con@Home

KATHMANDU: Three Disney+projects are coming to Comic-Con@Home — an online replacement of Comic-Con's annual San Diego expo between July 22 and 26. Anthology documentary series Marvel's 616, Phineas & Ferb, and The Right Stuff are three projects unveiled by Disney+ for the Comic-Con@Home Read More...

Coronavirus detected in drainage water in Kathmandu Valley

Kathmandu, July 4 Coronavirus has been detected in drainage water in two places of Kathmandu Valley. In samples collected from four places in the Valley, samples from two places came out positive for the virus. Report of a research conducted by Center for Molecular Dynamics Nepal 'Environmental Sur Read More...