Nepal | July 09, 2020

Tunnel digging of Bheri Babai diversion project expedited

Himalayan News Service
Share Now:

Kathmandu, January 4

The tunnel construction process of the Bheri Babai Diversion Multipurpose Project (BBDMP) has been expedited after the project started to dig the tunnel by utilising a tunnel boring machine (TBM). The project has adopted the TBM technology for the first time in the country to dig the 12-kilometre-long tunnel of the project.

After completion of the initial testing of the TBM on November 6, the project has dug 1,200 metres till date. The project is operating the machine 24 hours a day with two shifts being deployed for the purpose.

“The tunnel construction process is satisfactory and we expect the project to be completed within the set deadline of April, 2020,” said Rukmangat Khanal, senior divisional engineer of the project. “Before installing the machine, the project had dug 150 metres of the tunnel manually, but now the process has been expedited due to the TBM.”

According to the project, the TBM is being used to dig 20-25 metres of the tunnel per day, which is as per the plan of the project. “Overall 20 per cent progress has been achieved till now and if there is no further hurdle we will be able to complete the project as scheduled,” Khanal said.

The project had imported the TBM from China on September 15 and was deployed on September 25. According to Khanal, tunnel digging and cleaning process is continuing simultaneously.

The multipurpose project ill complete the tunnel digging process in the first phase. It will then construct the dam and hydropower plant in the second phase and the whole irrigation programme will be completed in the third phase.

As per the government’s plan, the multipurpose project will produce 48 megawatts of electricity and help irrigate 51,000 hectares of land in Banke and Bardiya districts. The powerhouse of the project will be constructed in Bheri Ganga municipality of Surkhet district.

Currently, the project is finalising the detailed study of the hydropower project and dam of the project. “It will be completed within the next few months and the work on the hydropower plant and dam will be started,” Khanal informed.

The government had initiated the project in 2011. As per the modality of the project, water from the Bheri River will be diverted to the Babai River and the multipurpose project will be completed. Due to delay in the construction of the tunnel, the overall progress of the project has been delayed.

Initially, six years back the government had estimated it would cost Rs 16.43 billion to complete the project. However, due to the delay in the progress of the project the total cost will increase. Then prime minister late Sushil Koirala had inaugurated the project on April 2, 2015. The government also listed the project as a national pride project.


A version of this article appears in print on January 05, 2018 of The Himalayan Times.


Follow The Himalayan Times on Twitter and Facebook

Recommended Stories:

More from The Himalayan Times:

Irrigation project elates farmers

NEPALGUNJ, JULY 7 Farmers in Banke were elated after Sikta Irrigation Project released water in the project’s western and eastern canals keeping in view the paddy plantation time this year. Man Bahadur Magar of Kamdi, Duduwa Rural Municipality, said he could plant paddy on time this year aft Read More...

Financial institutions, banks urged not to pile pressure for loan payment

POKHARA, JULY 7 Western Regional Hotel Association, Pokhara, has urged banks and financial institutions not to pile pressure for loan payment. Banks and financial institutions are pressing hotels and the tourism sector to pay back the loan and interest, on the ground that the fiscal year was d Read More...

Parliamentary committee probing irregularities

DHANGADI, JULY 7 The federal Parliament’s Agriculture, Cooperatives and Natural Resources Committee has started investigating alleged irregularities carried out in the name of scientific forest management. A team of the panel comprising Shanta Chaudhary, Satya Narayan Sharma Khanal and Raj B Read More...

‘Don’t just build back better, build back different’

According to the United Nations, the coronavirus pandemic is deepening pre-existing inequalities and exposing vulnerabilities in social, political and economic systems. The pandemic has compounded the socio-economic challenges facing women. Regarding this issue, Arpana Ale Magar from The Himalayan T Read More...

Helipads coming up in Banke, Bardiya

NEPALGUNJ, JULY 7 Local levels have started constructing helipads to control possible loss of lives and property due to floods in Banke and Bardiya. Helipad construction is under way to rescue people trapped in the floods. Choppers can take off and land even at night time in the new helipads. Read More...

Diprung Chuichumma RM to mobilise teachers in community from July 22

KHOTANG, JULY 7 Khotang’s Diprung Chuichumma Rural Municipality is preparing to mobilise teachers in every tole of the local level and resume teaching-learning activities from July 22. The rural municipality decided to this effect after the school remained closed for the past four months due Read More...

Hospitals to be upgraded next fiscal year

HETAUDA, JULY 7 Bagmati Province government will upgrade several hospitals in the province next fiscal. According to the Ministry of Social Development, the capacity of Hetauda Hospital will be upgraded to 300 beds. Bhaktapur, Sindhuli and Trishuli hospitals will be expanded to 100-bed hos Read More...

Making sure our four-legged friends are fed

KATHMANDU The lockdown came into effect in Nepal on March 24 to curb the spread of coronavirus confining people to their homes while schools, offices and businesses shut down. Nobody knew how the situation would unfold and for how long the lockdown would continue. At that moment Founder of Dis Read More...