Nepal | May 29, 2020

Delay in construction of transmission line worries hydel investors

Rastriya Samachar Samiti
Share Now:

Kathmandu, December 22

As many as three hydropower projects which are  set to generate power in near future are likely to face problem given the delay in construction of Kabeli Corridor transmission line.

Construction of the three hydropower projects, which would produce a total of 57 megawatts of electricity, will be completed by April, 2018. Industrialists have complained that power produced by the projects will be wasted as the Nepal Electricity Authority failed to expedite the construction of the transmission line.

Construction of 90 km transmission line from Padajungi of Jhapa to Amarpur of Panchthar is under way. The construction work is divided into three sections. Construction of the first section — Godak-Damak section — has been completed while two sections are still under construction. Construction of the transmission line started from the fiscal 2062/63. Currently the construction work is obstructed due to various reasons including compensation distribution.

Construction of 25 MW-Kabeli ‘B-1’ hydel project, 22 MW-Lower Hewakhola hydel power and 10 MW-Ewakhola hydropower project are in their final phase.

Chief of Kabeli ‘B-1’ hydel project, Ramesh Prasad Pokharel, said although the project was in final phase, chances of power being wasted were high because of NEA ‘s failure to construct 132-KV Kabeli Transmission Line on time.

Independent power producers said that the Indian construction company, which got responsibility of constructing Kabeli Corridor Transmission Line, did not prioritise the construction work.

Kabeli ‘B-1’ project is being constructed by the Arun Kabeli Hydroelectricity Project. Project chief Pokharel said they were likely to face problems as NEA did not pay attention to the construction of the Kabeli Corridor Transmission Line

The 22 kilowatt capacity Lower Hewakhola Project is also about to be completed. According to project chief Ganesh Subba, the project will be completed by April 7, 2018. He said they were preparing to connect the power generated from the project to the national grid through NEA’s sub-station located at Thapatar. Investors frequently complained about the problem to the NEA but all went down the drain.

Shailendra Guragain, the president of Independent Power Producers’ Association of Nepal, said that the projects that were nearing completion would face problems if the NEA did not become serious about constructing the power transmission line for the projects on time. He said the NEA should find out the reasons behind the delay and resolve the issues at the earliest.

However, the NEA has said that the construction work of the transmission line is going smoothly. Spokesperson of NEA, Prabal Adhikari said NEA chief executive officer Kulman Ghising had already given necessary instructions to the construction company to speed up the construction work. The NEA, nevertheless, said that the local administration had not been very much cooperative in expediting the construction work.

Locals are dissatisfied with compensation distributed for land which has caused problems in constructing as many 22 towers of the transmission line.

In this connection, the NEA has urged the Chief District Officer of Panchthar to use his good offices to settle compensation issue as soon as possible.


A version of this article appears in print on December 23, 2017 of The Himalayan Times.


Follow The Himalayan Times on Twitter and Facebook

Recommended Stories:

More from The Himalayan Times:

The office of the prime minister and council of ministers, OPMCM

Action plan to rescue Nepali citizens stranded abroad in a day or two

We’ll readily pay all our ticket and travel expenses and stay in quarantine for 14 days KATHMANDU, MAY 27 Nepalis, who had travelled abroad for non-employment reasons such as education, health and leisure and have been stuck there due to travel restrictions in place to contain the spread of co Read More...

Wage earners hit hard due to prolonged lockdown

Kathmandu, May 27 Padam Bahadur Thapa, 48 , who was spotted at Kaushaltar area of Bhaktapur at around 3:00pm, was riding a cycle cart to reach a house where he was assigned some work. He was promised Rs 200 for the work. Thapa is facing a hard time these days as his income has been limited Read More...

Lockdown silences traditional music of Gandharbas

Kathmandu Sanu Kanchha Gandharba has been playing sarangi since he was 12 years old. He followed his traditional profession, playing sarangi from village to village in Gorkha, Lamjung, Tanahun and Kaski. More than 30 years ago, he was drawn to Thamel and its tourists, and the prospect it offered Read More...

Kaligandaki Highway syangja

Three more test positive for COVID-19 in Syangja, Gandaki Province tally reaches 16

POKHARA: Three more persons have been detected with coronavirus transmission in Syangja district on Thursday, the Gandaki Province Health Directorate confirmed. According to Health Director Binod Bindu Sharma, two males aged 26 and 22 and a 39-year-old female of Waling Municipality tested positiv Read More...

UN: Virus could push 14 million into hunger in Latin America

BOGOTA: The UN World Food Program is warning that upward of at least 14 million people could go hungry in Latin America as the coronavirus pandemic rages on, shuttering people in their homes, drying up work and crippling the economy. New projections released late Wednesday estimate a startling in Read More...

Tourism stakeholders may be disappointed

KATHMANDU, MAY 27 Stakeholders of tourism industry — one of the hardest hit sectors due to the coronavirus pandemic — that are expecting to have their demands addressed through the budget may be in for a huge disappointment. The line ministry has said that the fiscal budget 2020-21 that is to Read More...

Martin Scorsese

Apple secures deal for Scorsese's next film starring DiCaprio, De Niro: media

Apple Inc has secured a deal for Hollywood veteran Martin Scorsese’s next film, “Killers of the Flower Moon,” US media reported on Wednesday, citing sources. “Killers of the Flower Moon” will star Leonardo DiCaprio and Robert De Niro. It is the second major film that Apple has acquired Read More...

In lean times, fierce dinosaur Allosaurus resorted to cannibalism

WASHINGTON: The dreaded dinosaur Allosaurus was the scourge of the Jurassic Period landscape some 150 million years ago, an apex predator just as Tyrannosaurus rex was 80 million years later during the Cretaceous Period. And, like T rex, Allosaurus may have engaged in cannibalism to keep i Read More...